PIPELINE PROJECTS
GAIL’s new pipelines – under implementation
(length and investment figures include spurlines)
|
| Sr. No. |
Pipeline |
Length |
Estimated Investment |
| 1. |
Chainsa – Jhajjhar – Hissar pipeline |
450 km. |
Rs. 1,250 crore |
2. |
Dadri – Bawana – Nangal pipeline |
610 km. |
Rs. 2,200 crore |
3. |
Dabhol – Bengaluru pipeline |
1,389 km. |
Rs. 4,543 crore |
4. |
Kochi – Kanjirkkod – Bengaluru – Mangalore pipeline |
1,114 km. |
Rs. 3,032 crore |
5. |
Capacity Augmentation
Dahej – Vijaipur section |
610 km. |
Rs. 5,000 crore |
6. |
Capacity Augmentation
Vijaipur – Dadri section |
505 km. |
Rs. 5,500 crore |
7. |
Jagdishpur – Haldia pipeline |
2,050 km. |
Rs. 7,600 crore |
8. |
Karanpur – Moradabad – Kashipur – Rudrapur pipeline |
275 km. |
Rs. 250 crore |
| 9. |
Capacity Augmentation
Bajera – Agra – Ferozabad section |
70 km. |
Rs. 200 crore |
|
 |